Request ID: FOI-1074-2122 Date published: 16 September 2021
You asked
1) How much has been spent on building the Creek Road section of Cycleway 4, which was completed earlier this year?
2) What is the budget for the decking works on Deptford Creek Bridge, which is being carried out by Greenwich Council but funded by TfL?
We answered
TfL Ref: FOI-1074-2122
Thank you for your request received by Transport for London (TfL) on 20 August 2021.
Your request has been considered in accordance with the requirements of the Freedom of Information Act and our information access policy. I can confirm that we hold the information you require. You asked:
1) How much has been spent on building the Creek Road section of Cycleway 4, which was completed earlier this year?
Creek Road build cost £4,248,004.13.
2) What is the budget for the decking works on Deptford Creek Bridge, which is being carried out by Greenwich Council but funded by TfL?
Deptford Creek Bridge - decking works budget is £250,000. Works are yet to start.
If this is not the information you are looking for, or if you are unable to access it for any reason, please do not hesitate to contact me.
Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed.
Yours sincerely
Eva Hextall FOI Case Management Team General Counsel Transport for London