FOI request detail

Update on Transport Developments for Buses & Rails

Request ID: FOI-0848-2425
Date published: 08 July 2024

You asked

Hey TfL, I just wanted to request if you can update me the current status on the progress of these ongoing bus & construction projects, and their estimated public opening dates (month & year if possible) as of mid-June 2024: 1) Cromwell Road Bus Station rebuilding 2) 281 bus's new terminus at Signal Park/ Toby Way/ Lansdowne Close/ Tolworth Station 3) Step-free Accessibility at: Tooting, Shortlands, Seven Sisters & Knightsbridge stations of the Tube Map 4) new Bakerloo line entrance at Paddington 5) new Stratford entrance 6) new Night Bus N518 7) new School Route 618 8) withdrawal of route 549 9) extension of route E1 10) renaming & colouring of the London Overground lines 11) resumption of 24-hour weekend night services on the 17 bus routes that were given Friday & Saturday night services to accompany the Night Tube since its very first day in 2016 until the pandemic (the latter of which has already resumed since 2021) 12) new Rolling Stock for the DLR, Bakerloo, Central, Piccadilly & Waterloo and City lines (New Tube for London) ...I am only looking for a date & an update on the current status on these developments, but if this list is still work-heavy for you and above the FOI limits, can you kindly please answer as many questions as you are able to in this list ranking instead please?

We answered

TfL Ref: FOI-0848-2425

Thank you for your request which we received on 13 June 2024. You asked for an update on the status of TfL’s bus and construction projects.

Your request has been considered in accordance with the requirements of the Freedom of Information Act and our information access policy.  I can confirm that we hold the information you require. You specifically asked about:

 

  1. Cromwell Road Bus Station rebuilding

 

This is published in Agenda item 6 - Investment Programme Report Quarter 4: 2023/24 (pages 21 - 82).

(Public Pack)Agenda Document for Programmes and Investment Committee, 26/06/2024 10:00 (tfl.gov.uk)

  1. 281 bus's new terminus at Signal Park/ Toby Way/ Lansdowne Close/ Tolworth Station

 

This is available on our website at: https://tfl.gov.uk/modes/buses/bus-changes?intcmp=47904#on-this-page-3  

From Saturday 6 July 24-hour route 281 will be extended from Tolworth Broadway to Tolworth Station via Tolworth Roundabout.

  1. Step-free Accessibility at: Tooting, Shortlands, Seven Sisters & Knightsbridge stations of the Tube Map

 

This project is being managed by Network Rail. Please refer to the following link for the latest information available on this project:

Tooting station Access for All Improvements - Network Rail

This project is being managed by Network Rail. Please refer to the following link for the latest information available on this project:

Shortlands station Access for All improvements - Network Rail

The Seven Sisters project has reached the delivery phase. The lifts are expected to be installed during the 2024/25 financial year. We are currently forecasting that they will be available for use by the public by late Summer 2025.

  1. new Bakerloo line entrance at Paddington

 

This is published in Agenda item 6 - Investment Programme Report Quarter 4: 2023/24 (pages 21 - 82). Refer to link above. 

5) new Stratford entrance

The new Southwestern entrance at Stratford should now be complete. 

6) new Night Bus N518

No decision has been made yet on the outcome of the consultation. Once a decision has been reached, it will be published here: https://haveyoursay.tfl.gov.uk/n518-ruislip-night-bus.

7) new School Route 618

This is likely to be at the start of the Autumn term 2024.  Details will be publicised on our website nearer the time.

8) withdrawal of route 549

It is expected that the restructuring of routes W12, W13 and W14 and withdrawal of route 549 will take place in September 2024.  Details will be publicised on our website nearer the time. 

9) extension of route E1

This is not expected to happen for a number of years. More information can be found here: https://haveyoursay.tfl.gov.uk/bus-routes-e1-618

10) renaming & colouring of the London Overground lines

Following a successful launch at Highbury & Islington station in February where the Mayor of London officially announced the new names and colours for the London Overground lines, the project is in full delivery mode.

Work to update signage across all 113 London Overground stations is progressing well. The redesign of our suite of maps and customer information products, such as the iconic Tube map and on-train maps, have begun and our customer journey planning tools such as TfL Go and Journey Planner, are also in digital development. Work to ensure our frontline colleagues are armed with the knowledge they’ll need to help customers with their journeys and provide excellent customer service when the line names come into use later this year has also begun. The project remains on track to complete by end of 2024.

12) new Rolling Stock for the DLR, Bakerloo, Central, Piccadilly & Waterloo and City lines (New Tube for London)

This is published in Agenda item 6 - Investment Programme Report Quarter 4: 2023/24 (pages 21 - 82). Refer to link above. 

In accordance with section 21 of the FOI Act, we are not obliged to supply you with a copy of the requested information as it is already accessible to you elsewhere.

If this is not the information you are looking for, or if you are unable to access it for any reason, please do not hesitate to contact me.

Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed. 

Yours sincerely

Eva Hextall 

FOI Case Management Team

General Counsel

Transport for London

 

Back to top