TfL updates on progress of Bank station upgrade as vital closure passes halfway mark

24 March 2022

Transport for London (TfL) is updating customers this week on the huge progress that has been made at Bank station since the Bank branch of the Northern line closed between Kennington and Moorgate in mid-January to finalise work on the new tunnel and customer concourse. This phase of the major upgrade work is on schedule to finish in mid-May, with the Northern line fully reopening to customers at this point.  

From this date, customers will benefit from a new, wider southbound Northern line platform, three new passageways to make moving through the station quicker and easier, and a spacious new concourse.  

The upgrade of Bank station will see its capacity increased by 40 per cent when work finishes later this year, with improvements still to come including step-free access to the Northern line and improved access to the DLR platforms. There will also be more direct routes within the station and a new station entrance on Cannon Street. Improving this station at the heart of London's financial district is critical to supporting the growth and success of the City, addressing long-standing capacity issues and making journeys through Bank safer, easier, quicker, and more comfortable when fully complete later in 2022.  

Work that has been completed during the closure at the halfway mark includes:  

  • Completing the excavation of the remaining 100m of new railway tunnel and lining it with sprayed concrete, in addition to the 2km that had already been tunnelled 
  • Connecting the new southbound Northern line tunnel to the existing railway 
  • Converting the former southbound Northern line platform, which was built more than 100 years ago, into a new, spacious customer concourse 
  • Installing the remaining 185m of track in the tunnels, in addition to the 490m that had already been laid 
  • Continuing with the fit-out of the new station areas, which includes flooring, wall coverings and signage on the new platform 
  • Preparing to run test trains through the new section of southbound tunnel from mid-April 

Stuart Harvey, Chief Capital Officer at Transport for London, said: "I'd like to thank our customers for their ongoing patience while a section of the Bank branch of the Northern line is closed. We have been making great strides in the intricate and complex work that is required below ground at Bank and are on schedule to finish this phase of the work in mid-May, as originally planned. Once complete, the improvements we're making at Bank station will be an important boost for the capital as the city continues to recover from the pandemic, giving London's financial district a modern, accessible, easy to navigate station fit for the twenty-first century."  

The key activities that are scheduled for the second half of the closure period include installing and testing all station systems, running test trains though the new southbound tunnel, and familiarising station staff with the new layout and systems.  

TfL is reminding customers to continue to check before they travel while the Bank branch of the Northern line between Kennington and Moorgate is closed, as many lines and stations across central London are busier as a result. Customers can check how busy their station is before they travel, using the TfL website's Journey Planner or via the TfL Go app.  

To further minimise the impact of the closure on journeys, customers are advised to: 

  • Travel at quieter times - the quieter times on the Tube and Rail network during the week are between 08:45 and 16:30 and after 18:45
  • Use alternative routes where possible - the Victoria and Bakerloo lines have plenty of space and may mean a more comfortable journey. There are also a number of National Rail routes that provide good alternatives such as Southeastern, Great Northern and Thameslink services 
  • Try using a different mode of transport - consider walking or cycling all or part of their journey, or use the local bus network 

Full travel advice is available at tfl.gov.uk/northern-line-closure

TfL's data indicates a shift to walking and cycling as a result of the closure, with a 31 per cent increase in Santander Cycle hires at key impacted cycle stations, and walking trips rising 28 per cent faster around the Bank area compared to the rest of the network. Demand for buses has also risen 20 per cent faster, on average, on impacted routes compared to the rest of the network. Customers are also reminded of the temporary bus route, the 733, which runs from Oval into the City on weekdays. 

As well as the work at Bank station, essential work is also being carried out at stations including London Bridge, Borough, and Elephant & Castle while the Northern line is closed so that future disruption can be minimised. This includes work on lifts and escalators, as well as refurbishment work at Borough and enabling works for the future Elephant & Castle station upgrade. 

Notes to editors

  • To help mitigate the closure of the Bank branch of the Northern line between Kennington and Moorgate (which also includes a reduced service between Camden Town and Moorgate), an enhanced service with a train at least every two minutes is running on the Charing Cross branch of the Northern line during peak periods. A new, additional bus route, the 733 from Oval into the City (Moorgate, Finsbury Square), has also been introduced on weekdays. It runs every 7-8 minutes to help affected customers reach their destinations. All other lines serving Bank station are unaffected by this closure
  • The Bank Station Capacity Upgrade project has been ongoing since 2016. More information is available on the project webpage at: gov.uk/travel-information/improvements-and-projects/bank-and-monument 
  • The track design of the Northern line means that Moorgate and Kennington are the only locations where trains can be turned around at either side of the Bank project work, which is why the closure is between these stations 
  • Much of the work completed for the project has been intricate and complicated, with 31 listed buildings at street level above the new tunnels, and foundations for other buildings that had to be tunnelled through. The work was completed by teams of engineers working in shifts around the clock, and despite the ongoing challenges presented by the pandemic, is on track to be delivered as planned later this year and within the £700m budget 
  • Additional Northern line closures are needed to complete this work, including:
  • Friday 15 April and Saturday 16 April between Charing Cross and Battersea Power Station, Euston and Stockwell (via Bank)
  • Saturday 23 April between Charing Cross and Battersea Power Station, Euston and Stockwell (via Bank)

Saturday 14 May and Sunday 15 May between Charing Cross and Battersea Power Station, Euston and Stockwell (via Bank)