Bank & Monument

Map of proposed changes at Bank and MonumentMap of proposed changes at Bank and Monument

Bank and Monument together are used by more than 52 million passengers a year. Demand has risen 50% over the last 10 years.

Improving the station is critical to keep London working and growing and is a key part of our plans to increase frequency on the Northern line.

Our plans

By 2021, the interlinked stations will feature several new escalators, a new station entrance and more room for Northern line passengers. This will increase capacity at the station by 40%.

The modernisation will include:

  • A new railway tunnel and platform for the Northern line that will reduce interchange times and create more space for passengers
  • Step-free access to the Northern line and DLR platforms
  • More direct routes within the station, with two new moving walkways
  • Two new lifts and 12 new escalators
  • A new station entrance in Cannon Street

Walbrook Square

The changes we intend to make are in addition to a new station entrance and step-free access to the Waterloo & City line from Walbrook Square. The new entrance will have two lifts, four escalators and a new ticket hall when it opens in late 2017.

Construction

More than 200 engineers and staff will work on site at Bank 24 hours a day until 2021.The station will remain open to customers throughout the work. Most of the construction work will take place below ground to minimise construction impact on the historically significant site which is bordered by 31 listed buildings.

Two main worksites are needed to construct the scheme:

  • The Cannon Street worksite is in the block bounded by Cannon Street, Abchurch Lane, King William Street and Nicholas Lane. The new station entrance, lifts and escalators will be built from this site. Demolition is preparing the site for the main upgrade works
  • Most of the tunnelling works will take place from the Arthur Street worksite. This means Arthur Street is closed to vehicles - however, pedestrians, dismounted cyclists and deliveries still have access

We aim to keep disruption to a minimum during construction and manage environmental impacts with industry best practices.

Transport and Works Act Order (TWAO)

We were granted a TWAO by the Secretary of State for Transport on Tuesday 15 December 2015. The TWAO authorises us to construct the works and operate the new section of railway.

The Secretary of State for Transport held a public inquiry into our application in April/May 2015. Our TWAO application documents, Statement of case, factsheets and settlement deed procedure are on the Bank station capacity upgrade page.

All other documents relating to the public inquiry, including those submitted by supporters and objectors are on the website of the Public Inquiry Programme Officer, Helen Wilson.

Northern line City branch - temporary closure

We will need to close part of the Northern line City branch in 2020 to connect new and existing sections of tunnel safely. Closures will be as shown below, with reduced frequencies on those sections of the City branch which remain open.

  • April - May 2020 (40 days): line closed in both directions Moorgate to Kennington
  • May - August 2020 (77 days):
    Northbound - trains not stopping at Bank
    Southbound - line closed Moorgate to Kennington

Alternative services

There will be room for displaced passengers on the District/Circle lines and Elizabeth line (currently being built by Crossrail Ltd), which will be fully operational by 2019. In addition, Thameslink frequency will be up to 24 trains per hour between Elephant & Castle/London Bridge, Blackfriars, City Thameslink and King's Cross.

To further help passengers, we will:

  • Run 33% more trains on the Northern line Charing Cross branch
  • Review bus use and consider enhancing services where necessary
  • Investigate scope for passengers to use alternative National Rail services, such as Waterloo to London Bridge, and London Bridge to Cannon Street
  • Review available walking space on the Moorgate to London Bridge pedestrian corridor

Timeline

  • 9 September 2014: Apply for Transport and Works Act Order (TWAO)
  • 28 January 2015: Pre-inquiry meeting at Glaziers Hall
  • 14 April 2015: Start of public inquiry at Glaziers Hall
  • 15 December 2015: TWAO decision
  • April 2016: Works start
  • April-August 2020: Northern line closure
  • July 2021: Works completed

Background

Between them, Bank and Monument stations are served by five Underground lines as well as the DLR.

Currently, 96,000 passengers use Bank station during the morning peak period, about 40,000 of whom are changing between lines.

The two stations consist of three ticket halls, six lifts, 10 platforms, 15 escalators and two 300-foot moving walkways, making one of the largest and most complicated subterranean railway complexes in the world.

Contact the Bank team

bankscu@tfl.gov.uk

Phone detailsPhone: 0844 332 8967 (24 hour helpdesk)

Close Favourites

My Lines

My Buses

My Roads

My River Buses

My Emirates Air Line

My Journeys

My Places

    Close edit Favourites

    Favourite lines

    Favourite buses

    Favourite roads

    Favourite river buses

    Favourite Emirates Air Line

    Favourite journeys

    Favourite places