FOI request detail

Kentish Town tube station works

Request ID: FOI-4489-2324
Date published: 02 April 2024

You asked

Please send me information regarding the project planning and construction works for Kentish Town tube station. Specifically: When construction work started. How many people were employed on site, on a month-to-month basis since the start of the works Specific details regarding what issues have been found that have delayed the reopening of the tube station including when these issues were found. Current estimation for the reopening of the tube station

We answered

TfL Ref: FOI-4489-2324

Thank you for your request received by Transport for London (TfL) on 2nd March 2024 asking for information about works at Kentish Town London Underground station.
 
Your request has been considered in accordance with the requirements of the Freedom of Information Act and our information access policy. 

I can confirm that we hold the information you require. Your questions are answered in turn below:

Question 1: When construction work started.

Answer: 28th June 2023.

Question 2: How many people were employed on site, on a month-to-month basis since the start of the works

Answer: Please see the table below. Note that on any given day there were an average of 16 people on site:
 
MonthTotal number of people on site
June 2023268
July 2023347
August 2023254
September 2023251
October 2023355
November 2023336
December 2023187
January 2024307
February 2024394


Question 3: Specific details regarding what issues have been found that have delayed the reopening of the tube station including when these issues were found.

Answer: The original work was to upgrade the escalators, and this is on track for completion in the summer. However, during work to improve other parts of the station we identified assets (including the ticket hall floor and ceiling) in December 2023 that require essential repair to allow the station to operate safely. Other work is being completed to improve the look and feel of the station including deep cleaning, painting, installing of new floor and wall tiling, and new signage. Further, following the commercial unit becoming vacant during the pandemic, some work has been undertaken to ensure that the space is ready to go back onto the market.

Question 4: Current estimation for the reopening of the tube station

Answer: September 2024.

If this is not the information you are looking for please do not hesitate to contact me.

Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed.

Yours sincerely,

David Wells
FOI Case Officer
FOI Case Management Team
General Counsel
Transport for London