Cost of two lifts with their columns and one walkway at Harrow-on-the Hill

Request ID: FOI-3222-1819
Date published: 15 March 2019

You asked

Dear Tfl Re.Harrow-on-the-Hill This is a drawing and reply that you kindly sent me last year.Please can you do a breakdown of the costs of the lift installation ,including building work to encase the lifts, of two of the lifts and one of the walkways. This is your FOI response from November for 4 lifts & all the walkways. Three lifts will be constructed to take the public from Ticket hall Level to platform level, one lift will be located on each island platform (1/2, 3/4 and 5/6), as shown in figure 1 below. The project also includes a fourth lift that will be built at the northern entrance to the station. cid:[email protected] Figure 1 – Computer Generated Image of the Concept Design (September 2017). The total build cost (including plant, material and equipment) is £4.6M Many thanks

We answered

TfL Ref: FOI-3222-1819

Thank you for your Freedom of Information request of 27th February 2019 asking for information about the cost of work to install new lifts at Harrow on the Hill station.

Your request has been considered in accordance with the requirements of the Freedom of Information Act and our information access policy. TfL does not hold the requested information, as explained below. Specifically you asked:

This is a drawing and reply that you kindly sent me last year. Please can you do a breakdown of the costs of the lift installation, including building work to encase the lifts, of two of the lifts and one of the walkways.

This is your FOI response from November for 4 lifts & all the walkways:

Three lifts will be constructed to take the public from Ticket hall Level to platform level, one lift will be located on each island platform (1/2, 3/4 and 5/6), as shown in figure 1 below. The project also includes a fourth lift that will be built at the northern entrance to the station.

We note that a breakdown of costs for the works at Harrow on the Hill was provided to you in our response of 12th February 2019, reference FOI-2965-1819. It is not entirely clear from your latest request what further breakdown of costs you are after. TfL does not have a contract in place for two lifts and one walkway at this station, and so cannot provide information on that basis – in essence, this would require us to put together a commercial estimate for a piece of work that does not exist in reality. The main contract for the works at Harrow on the Hill has been awarded on a lump sum basis, and it is highly unlikely that we could reliably break out the costs for more detailed individual elements.

Please see the attached information sheet for details of your right to appeal.

Yours sincerely,

David Wells

FOI Case Officer

FOI Case Management Team

General Counsel

Transport for London

Back to top

Want to make a request?

We'll email you the response within 20 working days.


We'll publish the response online without disclosing any personal information.