FOI request detail

Northern line track isolation upgrade update

Request ID: FOI-2589-2223
Date published: 01 February 2023

You asked

Follow-up to TfL Ref:2241-2223. Dear Jasmine, Thank you for this information. Would you be able to confirm the extent of the work in the vicinity of Camden Town as of 10:00 13th January 2023.

We answered

TfL Ref: 2589-2223
 
Thank you for your request received by Transport for London (TfL) on 13 January 2023 asking for information about London Underground’s Northern line track isolation upgrade in in the Camden Town area as of 10:00 on 13 January 2023, following your previous request for information, TfL reference number: 2241-2223
 
Your request has been considered in accordance with the requirements of the Freedom of Information Act and our information access policy.  I can confirm that we hold the information you require.

We can advise that on the northbound track in this vicinity, we have removed 120 Metres of Pandrol’s Vanguard Rail (PVR), completing 15.21% of this track upgrade overall.  .

Southbound, we have removed 120 metres of PVG, completing 14.66% of this site overall as part of the upgrade works taking place in the Camden Town area.

If this is not the information you are looking for, or if you are unable to access it for any reason, please do not hesitate to contact me.

Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed.

Yours sincerely



Jasmine Howard
FOI Case Officer
FOI Case Management Team
General Counsel
Transport for London