You asked

Good afternoon, Hope you're well. I am writing in regarding the noise on the eastbound Central line between Holland Park and Notting Hill Gate. While I appreciate there is no legal limit for noise on London Underground, the noise gets to the point that you cannot hear anything else and has set off warnings on various devices saying words to the effect of "Prolonged exposure to this noise is harmful for human hearing". Does TfL have any plans to tackle the noise, either by grinding or replacement of the track, and if so, when is this scheduled to take place? I note that I previously raised this to Customer Services and TfL responded on 23 Jan 2020 (reference CRM001:0975000003533) saying that the operative's understanding was that it would be done within the next couple of months. Judging by the fact that the noise has not changed on my many travels on the Central line, it would seem that nothing has happened for at least 3.5 years. I would also appreciate any maintenance logs for this bit of track which shows any grinding / track replacement / other maintenance works done to help reduce the noise levels within the past 5 years to confirm whether my understanding is correct. Do let me know if you need anything else. Best wishes

We answered

TfL Ref: EIR-2296-2324

Thank you for your request received by Transport for London (TfL) on 28th September 2023 asking for information about noise on the Central line.
 
Your request has been considered in accordance with the requirements of the Environmental Information Regulations and our information access policy. 

Specifically you asked:

I am writing in regarding the noise on the eastbound Central line between Holland Park and Notting Hill Gate. While I appreciate there is no legal limit for noise on London Underground, the noise gets to the point that you cannot hear anything else and has set off warnings on various devices saying words to the effect of "Prolonged exposure to this noise is harmful for human hearing".

Does TfL have any plans to tackle the noise, either by grinding or replacement of the track, and if so, when is this scheduled to take place? I note that I previously raised this to Customer Services and TfL responded on 23 Jan 2020 (reference CRM001:0975000003533) saying that the operative's understanding was that it would be done within the next couple of months. Judging by the fact that the noise has not changed on my many travels on the Central line, it would seem that nothing has happened for at least 3.5 years.

I would also appreciate any maintenance logs for this bit of track which shows any grinding / track replacement / other maintenance works done to help reduce the noise levels within the past 5 years to confirm whether my understanding is correct.”

I can confirm that we hold the information you require.

The table below shows the record of rail grinding that has taken place on the track between Holland Park and Notting Hill Gate in the last 5 years.
 
LineLCS CodeLCS DescriptionTotal LengthDriverMachineDateStartEndTotal
CENC136/CEBFAPLT2 HOLLAND PARK TOR TO PLT3 NOTTING HILL GATE TOR490RCF/CORRUGATIONRGU02/04/2019210380170
CENC136/CEBFAPLT2 HOLLAND PARK TOR TO PLT3 NOTTING HILL GATE TOR490PVRGU22/09/2019215438223
CENC136/CEBFAPLT2 HOLLAND PARK TOR TO PLT3 NOTTING HILL GATE TOR490PVRGU22/09/201943848547
CENC136/CEBFAPLT2 HOLLAND PARK TOR TO PLT3 NOTTING HILL GATE TOR490PVRGU26/01/2020170380210
CENC136/CEBFAPLT2 HOLLAND PARK TOR TO PLT3 NOTTING HILL GATE TOR490PVRGU26/01/2020380489109
 

More general maintenance that has taken place in the same period is shown in the table below. This work was all completed prior to 2020 and no other work has been undertaken since:

 
15231437Conductor Rail - Negative Ramp - HS & LS 65kg/m - Vertical Position (Mean Design Position - 33 mm for HS / - 35 mm for LS) - Max Deviation Of Lower End Of Ramp ML: - 14 mm to - 49 mm Below Top Of Running Rail Job Plan: CONDUCTOR RAIL MAINTENANCE < 90M - NIGHT POSITIVE AND NEGATIVE RAMPS NHG SUB GAPS RAIL GRINDING REQUIRED.
15231438Conductor Rail - Insulators - ML: 4 per 100m Cracked/Broken/Secured By Less Than 4 screws/Defective Packing Job Plan: CONDUCTOR RAIL MAINTENANCE < 90M - NIGHT BENCHING AROUND POSITIVE POT BROKEN
15231439Running Rail - Vertical Profile (long undulations - 5 metre intervals) - ML: 7 mm Job Plan: REALIGN TRACK (BALLASTED) - NIGHT CORRUGATION TO VANGAURD SITE

This stretch of track has been designated for further rail grinding to take place, currently scheduled towards the end of November 2023.

If this is not the information you are looking for please do not hesitate to contact me.

Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed.

Yours sincerely,

David Wells
FOI Case Officer
FOI Case Management Team
General Counsel