CycleWay 4, Old Street Roundabout, Highbury Corner and the upgrade of White Hart Lane Station projects

Request ID: FOI-2291-2021
Date published: 09 March 2021

You asked

Project or contract stage Information requested (see Annex 1 for clarification on the items listed below) Identification 1. Project reference number 2. Project owner 3. Sector, subsector 4. Project name 5. Project location 6. Purpose of the project 7. Project description 8. Officials assigned to the project and roles 9. Project brief or feasibility study Preparation 10. Project scope (main output) 11. Description of environmental impact 12. Description of land and settlement impact 13. Contact details of project owner 14. Funding sources 15. Project budget 16. Project budget approval date 17. Multi-year programme & budget 18. Environmental and social impact assessment 19. Resettlement and compensation plan 20. Financial agreement 21. Procurement plan 22. Project approval decision Tender (this applies to all tender processes developed for each project – eg. for design, construction, supervision, etc) 23. Procuring entity carrying out tender 24. Procuring entity contact details 25. Method of procurement process 26. Number of firms tendering 27. Cost estimate 28. Contract type signed with winner firm 29. Contract administration entity 30. Contract title 31. Contract firm(s) 32. Contract price 33. Contract scope of work 34. Contract start date 35. Contract duration 36. Contract status (current) 37. Procurement method 38. Tender documents 39. Tender evaluation results 40. Contract officials and roles 41. Contract agreement and conditions 42. Registration and ownership of firms 43. Specifications and drawings 44. Project design report Implementation (this applies to all contracts executed for each project – eg. for design, construction, supervision, etc) 45. Variation to contract price 46. Escalation of contract price 47. Variation to contract duration 48. Variation to contract scope 49. Reasons for price changes 50. Reasons for scope and duration changes 51. List of variations, changes, amendments 52. List of escalation approvals 53. Quality assurance reports 54. Disbursement records or payment certificates 55. Contract amendments Completion 56. Project status (current) 57. Completion cost 58. Completion date 59. Scope at completion 60. Reasons for project changes 61. Reference to audit and evaluation reports 62. Implementation progress reports 63. Budget amendment decision 64. Project completion report 65. Project evaluation report 66. Technical audit reports 67. Financial audit reports

We answered

TfL Ref: 2291-2021

Thank you for your email received by us on 10 February 2021 asking for information about Cycleway 4, the Old Street roundabout transformation, Highbury Corner and White Hart Lane Station projects.

Your request has been considered in accordance with the requirements of the Freedom of Information (FOI) Act and our information access policy.  I can confirm we do hold the information you require.
                                                                                                     
Some of the information you asked for is available on our website using various links provided below. For example, the supplier code reference numbers are referenced in documents published in the ‘Contracts, tenders and expenditure’ section for ‘contracts greater than £5000’. Plus, the earliest expiry date, value band and contract summaries can be found by using keywords of the projects in question to locate the referenced initiatives at: https://tfl.gov.uk/corporate/publications-and-reports/contracts-greater-than-5000

TfL’s procurement process is provided here: https://tfl.gov.uk/corporate/publications-and-reports/procurement-information?intcmp=3408

Link to contract finder: https://tfl.gov.uk/info-for/suppliers-and-contractors/

How TfL is funded: https://tfl.gov.uk/corporate/about-tfl/how-we-work/how-we-are-funded

Annual Reports and Statement of Accounts:  https://tfl.gov.uk/corporate/publications-and-reports/annual-report  https://tfl.gov.uk/corporate/transparency/audit-of-accounts---notice-of-public-rights

TfL’s Business Plan 2021-2024/25: http://content.tfl.gov.uk/tfl-business-plan-2019.pdf

Financial reports and budgets: https://tfl.gov.uk/corporate/publications-and-reports/business-plan?intcmp=3023

The Commissioner’s Report provides a review of the last four years of major developments: http://content.tfl.gov.uk/tfl-commissioners-report-18-march-2020.pdf ‘

Safety, Health and Environmental report: http://content.tfl.gov.uk/safety-health-and-environment-annual-report-2019-20.pdf

Integrated Impact Assessments: https://tfl.gov.uk/corporate/publications-and-reports/travel-in-london-reports#on-this-page-3

Sub-contractors and suppliers for White Hart Lane: https://tfl.gov.uk/corporate/transparency/freedom-of-information/foi-request-detail?referenceId=FOI-0138-1920

Sub-contractors for the Old Street project: https://tfl.gov.uk/corporate/transparency/freedom-of-information/foi-request-detail?referenceId=FOI-1685-1920

Highbury Corner project spend as of October 2019 and estimated final cost: https://tfl.gov.uk/corporate/transparency/freedom-of-information/foi-request-detail?referenceId=FOI-2237-1920
https://tfl.gov.uk/corporate/transparency/freedom-of-information/foi-request-detail?referenceId=FOI-1984-1920
                                               
Overviews of each project, their location, purpose and description:

https://tfl.gov.uk/travel-information/improvements-and-projects/cycle-superhighway-4

https://tfl.gov.uk/travel-information/improvements-and-projects/old-street-roundabout

https://tfl.gov.uk/info-for/media/press-releases/2020/october/major-work-to-transform-highbury-corner-is-complete

https://tfl.gov.uk/info-for/media/press-releases/2019/august/a-new-look-white-hart-lane-station-welcomes-customers

Additionally, the ‘Transforming Old Street roundabout’ consultation report, includes feedback from stakeholders including concerns on environmental impact, the background and purpose of the scheme: https://consultations.tfl.gov.uk/roads/old-street-roundabout/user_uploads/old-street-report-final.pdf

The Highbury Corner consultation report covers responses to issues raised regarding new layout: https://consultations.tfl.gov.uk/roads/highbury-corner-roundabout/user_uploads/highbury-corner-response-to-issues-raised.pdf

Cycle Superhighway 4 Tower Bridge to Greenwich consultation has responses to issues raised and discusses impact to cyclists: https://consultations.tfl.gov.uk/roads/cs4/user_uploads/cycle-superhighway-4-response-to-issues-raised.pdf

In accordance with section 21 of the FOI Act, we are not obliged to supply you with a copy of some the requested information as it is already accessible to you elsewhere.

Unfortunately, to provide the information you have requested in full would considerably exceed the ‘appropriate limit’ of £450 set by the Freedom of Information (Appropriate Limit and Fees) Regulations 2004.

Under section 12 of the FOI Act, we are not obliged to comply with a request if we estimate that the cost of determining whether we hold the information, locating and retrieving it and extracting it from other information would exceed the appropriate limit. This is calculated at £25 per hour for every hour spent on the activities described.

To help bring the cost of responding to your request within the £450 limit, you may wish to consider narrowing its scope so that we can more easily locate, retrieve and extract the information you are seeking. If you want to refine your request or make a Freedom of Information Act request in future, please bear in mind that the Freedom of Information Act allows you to request recorded information held by us. You should identify the information that you want as clearly and concisely as you can, specifying the types of document that you are looking for. You might also consider limiting your request to a particular period of time, geographical area or specific departments of the organisation.

Although your request can take the form of a question, rather than a request for specific documents, we do not have to answer your question if it would require the creation of new information or the provision of a judgement, explanation, advice or opinion that was not already recorded at the time of your request.

Please note that we will not be taking further action until we receive your revised request.

In the meantime, if you have any queries or would like to discuss your request, please do not hesitate to contact me.

Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed.

Yours sincerely

Jasmine Howard
FOI Case Officer
FOI Case Management Team
General Counsel
Transport for London
 

 