FOI request detail

More information needed re the Harrow-on-the Hill lift installation

Request ID: FOI-2207-1819
Date published: 18 December 2018

You asked

Please supply a breakdown of the programme and actual works that would be involved for the Harrow-on-the Hill Station lift installation project? How many of the six platforms are included in the scheme? Is there an outline/concept design drawing that would help me understand the extent and benefits of the project? Please can you also provide any indicative construction and equipment costs? I am not looking for a detailed breakdown of costs, only to understand what is involved (construction start time, installation time, testing time, opening time) in installing a lift system to a six platform station with step up and over entrances on both sides of the railway lines, served by many bus routes.

We answered

TfL Ref: FOI-2207-1819

Thank you for your request received by Transport for London (TfL) on 22 November 2018.

Your request has been processed in accordance with the requirements of the Freedom of Information Act and our information access policy. I can confirm we do hold the information you requested. You asked:

Please supply a breakdown of the programme and actual works that would be involved for the Harrow-on-the Hill Station lift installation project?

The indicative dates for each phase of the Step Free Access Project at Harrow-on-the-Hill are below. Please be aware these dates may change due to unforeseen circumstances.

Activity

Start

End

Early Enabling Works

Dec-17

March-19

Detailed Design

July-18

March-19

Construction of Main Works

March-19

Nov-19

Lifts Installation

(including Testing time)

Nov-19

March-20

(Lifts in use)

Finish on site

May-20

How many of the six platforms are included in the scheme? Is there an outline/concept design drawing that would help me understand the extent and benefits of the project?

Three lifts will be constructed to take the public from Ticket hall Level to platform level, one lift will be located on each island platform (1/2, 3/4 and 5/6), as shown in figure 1 below. The project also includes a fourth lift that will be built at the northern entrance to the station.

cid:image001.jpg@01D48714.F63410D0

Figure 1 – Computer Generated Image of the Concept Design (September 2017).

Please can you also provide any indicative construction and equipment costs? I am not looking for a detailed breakdown of costs, only to understand what is involved (construction start time, installation time, testing time, opening time) in installing a lift system to a six platform station with step up and over entrances on both sides of the railway lines, served by many bus routes.

The total build cost (including plant, material and equipment) is £4.6M

Please see the attached information sheet for details of your right to appeal.

Yours sincerely,

Melissa Nichols

FOI Case Officer

FOI Case Management Team

General Counsel

Transport for London

Back to top