You asked

Under the above Act I would be grateful if you would provide the information requested with regard to : The following document was made public by TFL: Programmes and Investment Committee Date: 13 October 2017 Item: Crossrail 2 It contains the following section : “4.3 Public consultation is critical to the Bill’s development. A consultation round is planned for January 2018, subject to Government approval of the updated SOBC. It is critical that, as a minimum, consultation is completed to enable the Safeguarding Directive to be updated to reflect the current proposed route, instead of the previous alignment.” 1. Would you detail the Change to the route from the previous alignment which are referred to and the new current proposed route? 2. In particular, what is the “current proposed route” between Victoria and Clapham Junction? 3. Given that a consultation on the proposed route is “planned for January 2018”, what will the consultation questions for the route between Victoria and Clapham Junction be?

We answered

TfL Ref: FOI-2133-1718

Thank you for your request received by Transport for London (TfL) on 02 November 2017 asking for information about Crossrail 2.

Your request has been considered in accordance with the requirements of the Environmental Information Regulations and our information access policy. I can confirm we do hold the information you require. You asked for the following:

1.Would you detail the Change to the route from the previous alignment which are referred to and the new current proposed route

2.In particular, what is the “current proposed route” between Victoria and Clapham Junction?

3. Given that a consultation on the proposed route is “planned for January 2018”, what will the consultation questions for the route between Victoria and Clapham Junction be?

We are not obliged to provide the requested information as it is subject to a statutory exception to the right of access to information under Regulation 12(4)(d) , which provides that a public authority may refuse to disclose information that relates to material which is in the course of completion, to unfinished documents or to incomplete data. The proposed route details, including any proposed alignment changes, and the consultation questions, are currently incomplete and will be published at the start of the next consultation, the date of which is to be confirmed.

This exception is subject to a public interest test, which requires us to assess whether the public interest in applying the exception outweighs the public interest in disclosure. In this instance, it is considered that the public interest favours the finalisation of the information, after all relevant factors can be taken into account, rather than the disclosure of information which does not accurately reflect any amendments that might still be made.

Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed.

Yours sincerely

Jasmine Howard
FOI Case Officer
Information Governance
Transport For London

 

Back to top

Want to make a request?

We'll email you the response within 20 working days.


We'll publish the response online without disclosing any personal information.