Woolwich Ferry

Request ID: FOI-1390-2223
Date published: 13 September 2022

You asked

Can you tell How Many days the Woolwich Ferry has been Suspended Since 31/10/21

We answered

TfL Ref: FOI-1390-2223

Thank you for your request of 20th August 2022 asking for information about the Woolwich Ferry.

Your request has been considered in accordance with the requirements of the Freedom of Information Act and our information access policy. 

Specifically you asked:

Can you tell How Many days the Woolwich Ferry has been Suspended Since 31/10/21?”.

I can confirm that we hold the information you require, which is provided in the tables below:

Number of days service suspended for a full day since 31st October 2021 = 119
 
Number of DaysReason
53Planned maintenance
21Unavailable resource / resilience levels
29Industrial Action
1Trials
3Technical / mechanical issues - Auto mooring units
12Safety critical infrastructure issues


Number of days service suspended for part of the day since 31st October 2021 = 48
 
Number of DaysReason
6High Tide
2High Winds
18Technical / mechanical issues with auto mooring units
5Unavailable resource / resilience levels
2Technical / mechanical issues - Linkspans
6Trials
5Technical / Mechanical issues - Vessels
1MCA Audit
3Other

If this is not the information you are looking for please do not hesitate to contact me.

Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed.

Yours sincerely,

David Wells
FOI Case Officer
FOI Case Management Team
General Counsel
Transport for London
 

Back to top

Want to make a request?

We'll email you the response within 20 working days.


We'll publish the response online without disclosing any personal information.