Crossrail opening
Request ID: FOI-1346-1920
Date published: 06 August 2019
You asked
After being delayed a number of years now, what will be the actual opening date of crossrail.
We answered
TfL Ref: FOI-1346-1920
Thank you for your email of 2nd August 2019 asking for information about the Crossrail project.
Your request has been considered in accordance with the requirements of the Freedom of Information Act and our information access policy.
Specifically you asked:
“After being delayed a number of years now, what will be the actual opening date of Crossrail.”
For the latest information about Crossrail, including details of the plan to deliver the outstanding works, please visit the Crossrail website via the following link:
http://www.crossrail.co.uk/news/articles/crossrail-project-update
In accordance with section 21 of the FOI Act, we are not obliged to supply you with a copy of the requested information as it is already accessible to you elsewhere.
If this is not the information you are looking for, or if you are unable to access it for any reason, please do not hesitate to contact me.
Please see the attached information sheet for details of your right to appeal.
Yours sincerely,
David Wells
FOI Case Officer
FOI Case Management Team
General Counsel
Transport for London