FOI request detail

Hammersmith Bridge

Request ID: FOI-1188-2021
Date published: 27 October 2020

You asked

- Amount spent on Hammersmith Bridge maintenance and monitoring since (and including) 2010. Please break this information down by year. - Details of annual payments made to engineering firms, construction companies or architects in relation to Hammersmith Bridge since (and including) 2010..

We answered

TfL Ref: FOI-1188-2021

Thank you for your request received by Transport for London (TfL) on 25 September 2020.

Your request has been considered in accordance with the requirements of the Environmental Information Regulations (EIRs) and our information access policy.  I can confirm that we hold some of the information you require. You asked:

- Amount spent on Hammersmith Bridge maintenance and monitoring since (and including) 2010. Please break this information down by year.

Please note that the LB Hammersmith & Fulham is the owner and highway authority for Hammersmith Bridge and we do not hold details of any expenditure they have incurred on the bridge.  However, we have been supporting the LB Hammersmith & Fulham for a number of years in developing refurbishment plans for the bridge and, in total, have spent £16.7m on assessments, feasibility, inspections and surveys, designs and other matters.  A breakdown is provided in the table below:

 

Amount (£m)

Reason

2007/08

£0.08

Assessment

2008/09

£0.13

Assessment

2010/11

£0.15

Investigation of weight limit enforcement and barrier/width restriction enhancement/improvements

2011/12

£0.34

Barrier/width restriction enhancement/improvements

2014/15

£0.20

Panels design

2015/16

£0.55

Reactive deck panel replacement

2016/17

£0.79

Reactive deck panel replacement / Pathway Stage 1 – Outcome definition, surveys and data collection

2017/18

£1.02

Pathway Stage 2 – Feasibility of options for repairing the bridge

2018/19

£1.70

Pathway Stage 2 – Feasibility of options for repairing the bridge

2019/20

£5.80

Pathway Stage 3 - Concept design for main bridge, investigation and early works on pedestals, design of temporary bridge and ongoing monitoring and inspections.

2020/21

£5.90

Pathway Stage 3 - Concept design for main bridge, detailed design for stabilisation works to make the bridge safe for the mainworks, investigation and early works on pedestals, concept design of temporary bridge and ongoing monitoring and inspections.

- Details of annual payments made to engineering firms, construction companies or architects in relation to Hammersmith Bridge since (and including) 2010.

As highlighted above, we do not have details of any payments made by the LB Hammersmith & Fulham. However, since taking responsibility for developing the designs for refurbishing the bridge in 2019/20, we have made the following payments to engineering firms and contractors working for us:

External Contracts

Activities

VOWD from P3 19/20 up to P7 20/21

Atkins

Responsible for Cat 2 and Cat 3 checks on mechanical equipment, structure, etc

£ 380,000

Mott MacDonald

Feasibility, surveys, monitoring, options assessment and technical approvals

£ 1,268,687

Pell Frischmann

Concept design for the Hammersmith Bridge strengthening and temporary bridge, together with detailed design for stabilisation works, planning and environmental assessments

£ 1,731,629

Costain

Construction and contracting advice for the main bridge works and temporary bridge

£ 786,559

Kier

Early investigative works to the bridge pedestals.

£ 3,438,064

If you are considering submitting a further request please think carefully about whether the request is essential at this current time, as answering FOI requests will require the use of limited resources and the attention of staff who could be supporting other essential activity. Where requests are made, please note that our response time may be impacted by the current situation.

If this is not the information you are looking for, or if you are unable to access it for any reason, please do not hesitate to contact me.

Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed.

Yours sincerely

Eva Hextall

FOI Case Officer

FOI Case Management Team

General Counsel

Transport for London