Request ID: FOI-1164-2122 Date published: 10 September 2021
You asked
Dear TfL,
In your most recent Investment Programme Report for Quarter 1 2021/22, the following notes are made (on page 22)
(https://content.tfl.gov.uk/pic-20210721-supplementary-agenda-papers-public.pdf):
"We continue to work with several stakeholders on an affordability study of HS2 in the Euston area. These stakeholders include HS2 Limited, Network Rail, the London Borough of Camden and Lendlease, under the umbrella of the newly formed Euston Partnership. HS2 Limited has presented a high-level proposal, with a detailed programme expected in July."
I have made an EIR/FOI request from HS2 for this 'high-level proposal'
as well as the 'detailed programme'. Unfortunately, HS2 Ltd have not been able to identify this document/proposal. I was wondering therefore if you could provide as much information as you can regarding this 'high-level proposal' and 'detailed programme' which was purportedly presented. This will aid HS2 in identifying any relevant documents.
We answered
TfL Ref: 1164 - 2122
Thank you for your request received by Transport for London (TfL) on 3 September 2021 asking for information about our Investment Programme Report for Quarter 1 2021/22. Your request has been considered in accordance with the requirements of the Freedom of Information Act and our information access policy. I can confirm that we hold the information you require.
The draft proposals and high level schedule were presented at the Euston Partnership Board on 8 April 2021 by High Speed Two (HS2) Limited.
If this is not the information you are looking for, or if you are unable to access it for any reason, please do not hesitate to contact me.
Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed.
Yours sincerely
Sara Thomas FOI Case Management Team General Counsel Transport for London