TfL Ref: FOI-0879-1920
Thank you for your email received by Transport for London (TfL) on 26 June 2019.
Your request has been considered in accordance with the requirements of the Freedom of Information Act and our information access policy. I can confirm we do hold the information you require. You asked:
Please supply all traffic light timing parameters for the pedestrian/cycle crossing on Holloway Road, adjacent to Whittington Park and Davenant Road.
In particular, the waiting time between a pedestrian or cyclist pressing a crossing button and the lights changing, and if and how it varies throughout the day.
The typical wait time for a pedestrian or cyclist after pressing the button will be between 0 and 45 seconds. In peak periods (7am to 10am and 4pm to 7:30pm), where traffic levels are higher and more people are travelling by bus, the maximum wait time is up to 65 seconds.
The traffic signal timings on this busy part of the A1 are coordinated and optimise automatically to seek to reduce delay to people travelling on the bus network. As traffic levels vary over the course of the day, so too does the maximum wait time.
If this is not the information you are looking for, or if you are unable to access it for some reason, please do not hesitate to contact me.
Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed.
Yours sincerely
Eva Hextall
FOI Case Officer
FOI Case Management Team
General Counsel
Transport for London
Back to top