FOI request detail

Forecast numbers of CLIP upgraded trains entering service each year until 2030

Request ID: FOI-0344-2425
Date published: 16 May 2024

You asked

The reply to a recent FOI request (ref: FOI-4278-2324) about the Central Line CLIP project included “we are now working for all the trains to be upgraded by the end of 2029”. What are the latest forecasts for the numbers of CLIP-upgraded 1992-Stock trains completed or entering service in each financial year from 2024/25 until 2029/30?

We answered

TfL Ref: FOI-0344-2425

Thank you for your request which we received on 29 April 2024.

Your request has been considered in accordance with the requirements of the Freedom of Information Act and our information access policy.  I can confirm that we hold the information you require. You asked:

 

What are the latest forecasts for the numbers of CLIP-upgraded 1992-Stock trains completed or entering service in each financial year from 2024/25 until 2029/30?

Please see the table below for our latest forecasts for CLIP trains into service:

Year

CLIP trains in service

FY24/25

2

FY25/26

9

FY 26/27

25

FY27/28

45

FY28/29

65

FY29

85

If this is not the information you are looking for, or if you are unable to access it for any reason, please do not hesitate to contact me.

Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed.

Yours sincerely

Eva Hextall 

FOI Case Management Team

General Counsel

Transport for London