FOI request detail

Ilford Station Rebuild Timeline

Request ID: FOI-0103-1819
Date published: 10 May 2018

You asked

Could you please let me know the timelines for Ilford Starion being rebuilt as part of crossrail plans. Your website here states it will b rebuilt as part of the programme: http://www.crossrail.co.uk/route/eastern-section/ilford-station

We answered

TfL Ref: FOI-0103-1819

Thank you for your request received by Transport for London (TfL) on 11 April 2018 asking for information about Ilford Station.

Your request has been considered in accordance with the requirements of the Freedom of Information Act and our Information Access Policy. I can confirm we do hold the information you require. You asked:

Could you please let me know the timelines for Ilford Station being rebuilt as part of Crossrail plans.

The timeline is as follows:

Outline design - Complete

Planning Permission – Granted

Detailed Design – In progress

Main construction contract award – Autumn 2018

Station opening commences – Dec 2019

Contractor off-site – Spring 2020

Please see the attached information sheet for details of your right to appeal.

Yours sincerely,

Melissa Nichols

FOI Case Officer

FOI Case Management Team

General Counsel

Transport for London