[A4] GREAT WEST ROAD (TW8) (Hounslow)
From: Wednesday 08 January 2025
To: Tuesday 14 January 2025
Last updated 18:23 Friday 10 January 2025 : Eastbound traffic queues are back to the junction with Windmill Lane. Expect delays.
Works | Utility works
[A4] Great West Road (All approaches) at the junction of Clayponds Lane - Lane restrictions and Clayponds Avenue is closed due to Cadent Gas Works.
Inner Ring
[A501] EUSTON ROAD (N1C,NW1,WC1H) (Camden)
From: Monday 06 January 2025
To: Thursday 27 February 2025
Last updated 18:17 Friday 10 January 2025 : Traffic is slow moving through the works. Expect delays.
Works | Utility works
[A501] Euston Road (Both directions) at the junction of [A4200] Upper Woburn Place - TfL drainage works - starts Upper Woburn Place, with temps - then Euston Road with lane restrictions to Gower Street. No works between 1800 20DEC24 and 0800 06JAN25.
[A1206] PRESTONS ROAD ROUNDABOUT (E14) (Tower Hamlets)
From: Monday 16 September 2024
To: Saturday 01 March 2025
Last updated 18:04 Friday 10 January 2025 : Eastbound congestion is occurring along Aspen Ways extending back towards Limehouse.
Works | TfL works
Silvertown Tunnel Scheme - Preston's Roundabout - [A1206] Prestons Road Roundabout (All directions) between [A1206] Prestons Road and [A1261] Aspen Way - Lane restrictions are in place to facilitate Silvertown Tunnel related works.
A13
[A13] NEWHAM WAY (E16) (Newham)
From: Thursday 19 December 2024
To: Sunday 25 May 2025
Last updated 17:44 Friday 10 January 2025 : Currently traffic flows are normal for the time of day.
Works | TfL works
Canning Town Flyover Refurbishment Works - [A13] Newham Way (Both directions) between [A13] East India Dock Road and Beckton Road - Lane closures and restrictions in place for flyover refurbishment works.
Bishopsgate Cross Route
KING WILLIAM STREET (EC3V,EC4N,EC4R) (City of London)
From: Monday 08 July 2024
To: Wednesday 31 December 2025
Last updated 07:08 Friday 10 January 2025 : Use an alternative route. Delays are possible on diversion.
Works | Borough works
King William Street (Southbound) at the junction of Lombard Street - Road closed to facilitate urban realm works.
Silvertown Tunnel, Greenwich Peninsula () ()
From: Friday 25 February 2022
To: Friday 28 February 2025
Last updated 14:34 Friday 10 January 2025 : Delays are possible.
Works | TfL works
Silvertown Tunnel project, Greenwich Peninsula - Various restrictions during Silvertown Tunnel-related works until 2025. Millennium Way is currently closed. There are associated lane closures on the northbound A102 Blackwall Tunnel Southern Approach. https://tfl.gov.uk/travel-information/improvements-and-projects/silvertown-tunnel for More information.
[A118] HIGH STREET (E15,E3) (Newham,Tower Hamlets)
From: Monday 09 September 2024
To: Friday 28 February 2025
Last updated 17:45 Friday 10 January 2025 : Expect delays throughout the course of the works. Currently traffic flows are normal for the time of day.
Works | TfL works
[A118] High Street (All approaches) at the junction of [A11] Bow Road - Lane closures on all approaches and on the roundabout, and closure of the link road under the flyover due to Sivertown Tunnel works.
[A404] HIGH ROAD (HA0,HA9) (Brent)
From: Wednesday 08 January 2025
To: Friday 10 January 2025
Last updated 18:09 Friday 10 January 2025 : Delays on approach with westbound traffic on High Road tailing back beyond Wembley Hill Road. Additional delays on all adjoining roads. Expect delays.
Works | Utility works
[A404] High Road (Both directions) at the junction of [A4089] Ealing Road - Temporary traffic signals in use to facilitate UKPN works.
[A503] CAMDEN ROAD (N7,NW1,NW5) (Camden,Islington)
From: Thursday 09 January 2025
To: Saturday 11 January 2025
Last updated 18:19 Friday 10 January 2025 : Minor delays on approach with southbound traffic on Camden Road tailing back to Brecknock Road and northbound traffic tailing back beyond Royal College Street. Expect delays.
Works | Utility works
[A503] Camden Road (Both directions) at the junction of Sandall Road - Temporary traffic signals are in operation to facilitate Thames Water works.
A406
[A406] NORTH CIRCULAR ROAD (NW10,NW2) (Brent)
From: Friday 10 January 2025
To: Ongoing
Last updated 18:19 Friday 10 January 2025 : Queues are back to Neasden Lane. Expect delays.
Works | Utility works
[A406] North Circular Road (Westbound) between Aboyne Road and The Circle - Lane one (of three) is closed due to facilitate utility repair works.