A12 George Green Tunnel Repair Works
Following a serious road traffic accident which damaged the tunnel lighting, a number of planned closures have been organised in order to repair the damage and ensure high safety standards are maintained in the tunnel.
The westbound bore of the tunnel will close for repairs, with traffic being transferred to the eastbound bore under contra-flow. The planned closure times are from 21.00 on Friday until 05.00 Monday on the following dates:
- 12/3 - 15/3
- 19/3 - 22/3
- 2/4 - 5/4
- 23/4 - 26/4
- 7/5 - 10/5
TfL apologises for any disruption these essential repair works may cause to drivers.
These works have been planned to avoid the major football games and local events planned for the area and to take advantage of lighter weekend traffic.
As London's population continues to grow there will increasing demands placed on our public transport system and TfL aims to deliver the improvements that will match London's future needs. This can only be achieved with continued support from Government. TfL will balance its budget whatever happens but without additional funding essential sustained improvement to the road network will not take place.
Anna Brosnan
Press Office
Email: annabrosnan@tfl.gov.uk
Direct line: 020 7941 4376