The track and drainage is being replaced to increase reliability and shorten journey times. This section of line runs in single bore tunnels which means there is less room to work in than on other parts of the network.

To speed up the work by allowing contractors longer on site each night, the line will close early between Aldgate and Wembley Park on Mondays, Tuesdays and Wednesdays.

These closures will not take place on Bank Holidays and for some Wembley events.

Travel options

A revised Metropolitan line service will operate north of Wembley Park:

  • Wembley Park to Amersham - every 30 minutes
  • Wembley Park to Chesham - every 30 minutes
  • Wembley Park to Uxbridge - every 10 minutes
  • Harrow-on-the-Hill to Watford - every 15 minutes

Use the Jubilee line for travel between Wembley Park and Baker Street.

Use the Circle or Hammersmith & City line for travel between Baker Street and Aldgate.

Chiltern Railways services also run between Amersham, Chalfont & Latimer, Chorleywood, Rickmansworth, Harrow-on-the-Hill and Marylebone.

Revised first and last train times

Last Metropolitan line through trains to central London

 From  To
 Mondays - Wednesdays
 Amersham  Aldgate
 20:47
 Chesham  Baker Street
 21:03
 Uxbridge  Aldgate  21:27
 Watford  Aldgate  21:13
 Wembley Park
 Aldgate  21:54

Later trains run on all branches. After the times above, change at Wembley Park for the Jubilee line to Baker Street.

Last Metropolitan line through trains from central London

 From  To  Mondays - Wednesdays
 Aldgate  Amersham  22:17
 Aldgate  Chesham  22:32
 Aldgate  Uxbridge  22:22
 Baker Street
 Watford  22:13

Later trains run between Wembley Park and Amersham, Chesham and Uxbridge. Later trains run between Harrow-on-the-Hill and Watford.

Last Chiltern Railways services

 From
 To  Mondays - Wednesdays
 Marylebone  Amersham  23:57
 Amersham  Marylebone  23:09

First Metropolitan line through trains from Baker Street

 To
 Tuesdays - Thursdays
 Amersham  06:31
 Chesham  06:24
 Uxbridge  05:58
 Watford  05:53

Earlier trains on the Watford branch run from Harrow-on-the-Hill and on all other branches from Wembley Park.

First Metropolitan line through trains to central London

 From  To  Tuesdays - Thursdays
 Amersham  Aldgate  05:26
 Chesham  Aldgate  05:56
 Uxbridge  Baker Street
 05:12
 Watford  Aldgate  05:29
 Wembley Park
 Baker Street
 05:28

First Jubilee line trains (Tuesdays - Thursdays)

 From
 Departs
 To  Arrives
 Baker Street
 05:42  Wembley Park
 06:01
 Wembley Park
 05:05  Baker Street
 05:22