The West End Project is being built by the London Borough of Camden. TfL have part-funded this scheme.

We plan to switch Tottenham Court Road to two-way traffic on Saturday 20 April 2019.


Driving

Monday 18 March to Wednesday 17 April 2019

We will be completing carriageway resurfacing works on Tottenham Court Road, which will be reduced to one lane at all times. If possible, use public transport for travel to the area.

If you have to drive to the area, some side roads accessing Tottenham Court Road will be closed during the resurfacing works - check the Camden website for details.

Key changes on Saturday 20 April on Tottenham Court Road:

  • Tottenham Court Road will be switched to two-way traffic
  • The new southbound lane will be for buses and cyclists only at all times until spril 2020
  • All traffic can continue to travel northbound until the entire scheme is completed in spring 2020

There are more details and maps on Camden's project website.


Cycling

Key changes affecting cyclists from Saturday 20 April:

  • Tottenham Court Road will be switched to two-way traffic
  • Signs will be in place to help cyclists during the works
  • To avoid the works, cyclists can use Quietway 1 (North): Covent Garden to Tavistock Place
  • The new southbound lane will be for buses and cyclists only at all times until spring 2020
  • All traffic can continue to travel northbound until the entire scheme is completed in spring 2020

If you want to hire a Santander Cycle, you can check availability  using the online docking station map. Follow @SantanderCycles for news and customer service.

Download the Santander Cycles app from the App Store or Google Play.


Buses

Resurfacing works on Tottenham Court Road

Services will continue, but some bus stops on Tottenham Court Road will be temporarily closed to make works possible.

From 08:00 on Monday 25 March to 16:00 Friday 26 April, routes 19, 38, N19, N38 and N41 towards Battersea/Victoria/Trafalgar Square will be on diversion via Drake Street and Proctor Street.

From 08:00 Monday 8 April to 22:00 Wednesday16 April 2019, route 14 will not serve southbound stops on Gower Street or northbound stops on Tottenham Court Road.

Route 14 will terminate at Tottenham Court Road Station. Use alternative bus routes to travel to and from University College Hospital. Route 176 towards Tottenham Court Road will be shortened and finish at stop A on Charing Cross Road.

See the signs at bus stops for more information.

From Saturday 20 April

Both northbound and southbound buses will use Tottenham Court Road. Buses will no longer run along Gower Street/Bloomsbury Street. This will be a permanent change.

Find out how your bus may be affected on our Bus status updates map.

Follow @TfLBusAlerts for news and service information.


New bus arrangements from 20 April 2019


Pedestrians

Tottenham Court Road will be switched to two-way traffic - take care crossing.

Shops and businesses in the area will be open throughout the works, and pedestrian access will be maintained.


Freight, deliveries and servicing

Loading bays will need to be suspended at times for works. These temporary changes will be clearly signed.

The project team is continuing to work with local businesses to provide advice and to ensure that you can make and receive deliveries during construction.

If you make or receive deliveries in the area, talk to your customers and suppliers now to see if there are changes you need to make to your deliveries or collections, such as moving them to outside the restricted periods. Find out more about changing your deliveries.


About the scheme

Work will be completed in spring 2020.

Find out more about the scheme on Camden's project webpage.