Rotherhithe-Canary Wharf
Request ID: FOI-1803-1819
Date published: 05 November 2018
You asked
The total taxpayer spend on the proposed Rotherhithe-Canary Wharf bridge to date (8th October 2018)
We answered
Dear
TfL Ref: FOI-1803-1819
Thank you for your email received by Transport for London (TfL) on 8 October 2018, asking how much was spent on the proposed Rotherhithe-Canary Wharf river crossing to date.
Your request has been considered in accordance with the requirements of the Freedom of Information Act and our information access policy. I can confirm we do hold the information you require.
The total spend as of 13 October 2018 on this river crossing project is £7.32 million. This funding covers initial optioneering, delivery and analysis of the first public consultation, as well as modelling and engineering design work towards a preferred option ahead of a second public consultation on the proposed crossing.
If this is not the information you are looking for, or if you are unable to access it for some reason, please do not hesitate to contact me.
Please see the attached information sheet for details of your right to appeal as well as information on copyright and what to do if you would like to re-use any of the information we have disclosed.
Yours sincerely
Eva Hextall
FOI Case Officer
Transport for London
Under the FOI Act please could you provide the following :
1) The total taxpayer spend on the proposed Rotherhithe-Canary Wharf bridge to date (8th October 2018)
Back to top