2. Initial procedure for proposing a Change

2.1 If a party wishes to propose a Change, it shall raise such proposal for discussion ( or other consideration ) at one of the reviews referred to in paragraph 1.2 above where all parties affected have participated.

2.2 Provided the proposed Change has been discussed at a review meeting, the party proposing a Change shall submit a plan ( Change Implementation Plan ) ( in accordance with clause 55.1 ( Notices ) of the Service Contracts ) to the other parties containing the following information:

(a) full details of the nature of the proposed Change;
(b) the date of implementation of the Change, such date not being less than six (6) months from the date of receipt of the Change Implementation Plan by the recipient(s); and
(c) the expected level of capital expenditure ( if any ) to be incurred by any of the parties, individually or collectively, in order to implement the Change.

2.3 In determining the date of implementation, the party proposing the Change shall have regard to:

(a) the need for all parties affected to give reasonable consideration to the effects of the proposed Change;
(b) the time needed to ensure that the Change Conditions set out in paragraph 3.1 below ( if applicable ) have been or will be complied with by the date of implementation; and
(c) the time needed for the parties affected to implement the Change.