SCHEDULE 5.17 - Form of Notice of Instruction (Disputes)

On LUL letterhead


To Infraco
Attention: [_____ _____]

LUL Contract Manager Third Party Notice Reference [_____ _____]

The undersigned as a duly authorised representative of LUL hereby certifies that it is necessary pending final resolution of the Dispute involving [_____ _____] for Infraco to take the action and steps set out below to avoid LUL being in breach of its obligations to [ identify third party ].

LUL hereby instructs Infraco to immediately take the following action and steps: [_____ _____]

LUL requires Infraco to take the action and steps set out above until an Adjudicator has rendered his decision in accordance with the provisions of the Dispute Resolution Agreement or until such time as Infraco is instructed otherwise by LUL, whichever shall be the first to occur.

Yours faithfully

_________________________
for and on behalf of LUL