SCHEDULE 5.15 - Form of Corrective Action Notice |
|
To: Infraco From: LUL Date: _____ _____ Sequence number : [ insert unique reference number] Notice to take corrective action This notice is given pursuant to clause [_____ _____ ] of the contract between us dated [_____ _____ _____ ] ( as may be amended from time to time ) ( the Contract ). Terms defined in the Contract shall bear the same meanings herein. LUL hereby gives notice that Infraco have defaulted in the performance of Infraco's obligations under the [ specify relevant Transaction Document ] in the following respect: [ insert details of default ]. LUL hereby notify Infraco that within [_____ ] days of receipt of this notice Infraco is required to carry out corrective action to remedy the above default. Yours faithfully The Contract Manager for and on behalf of LUL |